§ 70-514.10. Process for approval of engineering plans.  


Latest version.
  • (a)

    Engineering plans for the design and construction of required public facilities shall be submitted with the final plat. The agent shall approve or disapprove plans within 60 days of their submission. If state agency (VDOT and/or health department) approval of the engineering plans is required, the agent shall approve or disapprove the plans within 60 days of the receipt of the state agency approval. In the event of the failure of the agent to act within such periods, the plans may be submitted, after ten days' notice to the county, to the board of supervisors for its approval or disapproval.

    (Ord. No. O-09-02, 1-27-2009)