§ 70-516.16. Final plat—Recordation in phases.  


Latest version.
  • (a)

    If the subdivider prepares for recordation a final plat which is a section or phase of a subdivision as shown on the approved preliminary plat within the period established in section 70-516.8 above, then the subdivider may prepare the remaining sections or phases within a period of five years from the recordation date of the first section, in accordance with this section. The subdivider shall furnish the county with a certified check, cash escrow, bond, or irrevocable letter of credit in the amount of the estimated cost of construction of the facilities to be dedicated within said section or phase for public use by the county, the commonwealth, or other public agency. The five-year time period provided herein may be extended for a period not to exceed one year by the agent at the time of approval of the preliminary plat, as provided in section 70-512.10 above.

    (Ord. No. O-09-02, 1-27-2009)