§ 70-602.2. Time of agreement.  


Latest version.
  • (a)

    The period within which improvements or installations shall be completed and inspected for acceptance shall be specified in the subdivision agreement. In approving the time of performance of the subdivision agreement, the agent shall require a report containing the following information from the subdivider:

    (1)

    Percent of public improvements already completed; and

    (2)

    Rate of construction activity including the estimated completion date for each major feature (roads, sidewalks, sewer, water, lights, etc.) remaining to be completed.

    (b)

    The agent shall not permit a subdivision agreement to be executed where, on the basis of the report submitted by the subdivider, it is apparent that the improvements or installations covered by said agreement cannot reasonably be expected to be completed by the deadline established therein.

    (Ord. No. O-09-02, 1-27-2009)