§ 82-261. Connection charge schedule.  


Latest version.
  • (a)

    For residential customers using a standard three-quarter inch service pipe and a five-eighths inch meter, the connection fee shall be $3,000.00. Connection fees for meters larger than five-eighths inch shall be in accordance with subsection (b) of this section.

    (b)

    Connection fees for customers requiring eight-inch or smaller meters shall be based upon the installed meter size according to the following schedule:

    Meter Size Connection Fee
    5/8 ″ $3,000.00
    ¾″ 3,000.00
    1″ 11,230.00
    1½″ 23,420.00
    2″ 38,670.00
    3″ 80,840.00
    4″ 133,610.00
    6″ 259,930.00
    8″ 399,630.00

     

    Connection fees for customers requiring larger than eight-inch meters shall be determined on a case by case basis and established by contract, but in no case shall be less than the capacity fee for an eight-inch meter.

    For meter sizes eight-inch and smaller, if an existing customer desires to redevelop and replace an existing meter with a single or multiple meters, the value of the connection fee associated with the existing meter shall be determined based on the fee schedule above and credited for use on the property. For customers with meters larger than eight inches, the property will be credited the value of a eight-inch meter connection fee unless documentation of payment of a greater connection fee is provided, in which case the connection fee credited shall be the actual amount paid. Once a connection fee has been credited to a property, the amount of the credit is fixed and available for use on the property. Refunds shall not be made for any unutilized amount.

    Notes:

    1.

    For single-family dwellings served by a private water supply at the time a newly constructed utility line is completed, a discount in the list connection charges may be offered, subject to the conditions of section 82-110.

    2.

    Developer-installed charge shall be assessed for each single-family residential unit, as defined in section 82-31, included in the development connecting to a line installed by the developer or any subsequent owner of the lot or premises within the development. Commercial or industrial uses included in any development shall be assessed at the charges listed in the schedule. Developer-installed connection charges shall be subject to the credits provided for in section 82-73.

    3.

    If the service connection has not been installed during the initial construction, the lot owner would be responsible for the installation costs as well as the connection fee listed.

    (Code 1988, § 16-176; Ord. No. O-00-006, 5-9-2000; Ord. No. O-01-006, 8-22-2001; Ord. No. O-03-003, 8-13-2003; Ord. No. O-08-10, 11-12-2008; Ord. No. O-14-023A, § 1, 10-14-2014; Ord. No. O-16-06, § 1, 7-12-2016; Ord. No. O-19-03, § 1, 3-26-2019)

(Code 1988, § 16-176; Ord. No. O-00-006, 5-9-2000; Ord. No. O-01-006, 8-22-2001; Ord. No. O-03-003, 8-13-2003; Ord. No. O-08-10, 11-12-2008; Ord. No. O-14-023A, § 1, 10-14-2014; Ord. No. O-16-06, § 1, 7-12-2016; Ord. No. O-19-03, § 1, 3-26-2019)